Provides requirements for implementing On-The-Spot Changes (OTSCs) to technical and implementing procedures, including criteria for what constitutes a change to the intent of a procedure.
Key Actions / Information
Exam — 2022 Q69
Altering an Inspection Hold Point is considered a change to the INTENT of a procedure and must go through the formal procedure change process (cannot be done via OTSC). The following are NOT changes to intent and CAN be done via OTSC: increasing management oversight/approval level, adding clarifying text to a step, and correcting a step reference to the correct attachment.