SALEM
SALEM STUDY SYSTEM
Tech Specs > TS 3/4.5 — ECCS

TS 3/4.5 — ECCS

⚠️ DRAFT

TS 3/4.5 — Emergency Core Cooling Systems

Accumulators

LCO 3.5.1
Each RCS accumulator shall be OPERABLE with:
a. Isolation valve open
b. Contained volume: 6223–6500 gallons
c. Boron concentration: 2200–2500 ppm
d. Nitrogen cover-pressure: 595.5–647.5 psig

Applicability: Modes 1, 2, and 3 (pressurizer pressure >1000 psig)

Actions:

ConditionRequired ActionCompletion Time
1 accumulator inoperable (not isolation valve or boron)Restore to OPERABLE24 hrs, or Hot Shutdown in 12 hrs
1 accumulator inoperable due to closed isolation valveImmediately open valveOr Hot Standby in 24 hrs + Hot Shutdown in 12 hrs
1 accumulator boron concentration outside limitsRestore boron concentration72 hrs, or Hot Standby in 6 hrs and reduce PZR pressure to ≤1000 psig in 6 hrs

Amendment No. 282

▶ Bases — 3/4.5.1 Accumulators
Bases — 3/4.5.1

Each accumulator provides a passive, immediate surge of borated water into the core through each cold leg when RCS pressure falls below accumulator pressure. No electrical power or actuation signal is required — this initial surge provides the critical first cooling mechanism during large RCS pipe ruptures.

The limits on accumulator volume, boron concentration, and nitrogen cover-pressure ensure that the assumptions used for accumulator injection in the safety analysis are met.

The accumulator power-operated isolation valves are considered “operating bypasses” per IEEE Std 279-1971, which requires bypasses of a protective function to be removed automatically when permissive conditions are not met. Because these valves fail to meet single-failure criteria, power must be removed from the accumulator isolation valves.

If a closed isolation valve cannot be immediately opened, the full capability of one accumulator is not available and prompt action is required to place the reactor in a mode where this capability is not required. Operating with one accumulator inoperable (for reasons other than a closed isolation valve or boron concentration) is limited to 24 hours to minimize exposure to a LOCA concurrent with failure of an additional accumulator that could result in unacceptable peak cladding temperatures.

Exam — 2018 Q86
Accumulator boron concentration limits: 2200 - 2500 ppm. Sample results: 21 at 2175 ppm (below 2200 → inoperable), 22 at 2550 ppm (above 2500 → inoperable), 23 at 2400 ppm (within limits → operable), 24 at 2350 ppm (within limits → operable). Result: 2 accumulators inoperable. LCO 3.5.1 action only addresses ONE accumulator inoperable due to boron (72 hrs + 6 hrs to Hot Standby). With TWO inoperable, no applicable action exists → LCO 3.0.3 applies: 1 hr + 6 hrs = 7 hours to HOT STANDBY. 78 hours (72 + 6) would only be correct if one accumulator were inoperable. With two inoperable, there is no action that addresses the condition and LCO 3.0.3 is the default.

ECCS Subsystems — Tavg ≥ 350°F

LCO 3.5.2
Two independent ECCS subsystems shall be OPERABLE, each comprised of:
a. One centrifugal charging pump + flow path (cold leg injection)
b. One safety injection pump + flow path (cold leg injection; manual hot leg injection)
c. One RHR pump + RHR HX + flow path (cold leg injection)

Applicability: Modes 1, 2, and 3

Actions:

ConditionRequired ActionCompletion Time
1 ECCS subsystem inoperableRestore to OPERABLE72 hrs, or Hot Shutdown in 12 hrs
Both ECCS subsystems inoperable (surveillance testing)Restore at least one1 hr, or Hot Standby in 6 hrs + Hot Shutdown in 6 hrs + Cold Shutdown in 24 hrs

Key Surveillance Requirements:

SRRequirementFrequency
4.5.2.aVerify specific valves in correct position with power removed (see valve list below)Per SFCP
4.5.2.eVerify auto-start of charging, SI, and RHR pumps on SI test signalPer SFCP (during shutdown)
4.5.2.fVerify pump TDH per IST program: Charging ≥2338 psi, SI ≥1369 psi, RHR ≥165 psiPer IST

ECCS Valve Alignment (SR 4.5.2.a)

ValveFunctionRequired Position
2 SJ 69RHR pump suctionOpen
2 SJ 30SI pump suctionOpen
21 SJ 40SI discharge to hot legsClosed
22 SJ 40SI discharge to hot legsClosed
2 RH 26RHR discharge to hot legsClosed
21 SJ 49RHR discharge to cold legsOpen
22 SJ 49RHR discharge to cold legsOpen
2 SJ 135SI discharge to cold legsOpen
21 RH 19RHR crosstie valveOpen
22 RH 19RHR crosstie valveOpen

Amendment No. 282

▶ Bases — 3/4.5.2 ECCS Subsystems (Tavg ≥ 350°F)
Bases — 3/4.5.2

Two independent ECCS subsystems ensure that sufficient emergency core cooling capability is available assuming any single active failure in either subsystem. Either subsystem operating in conjunction with the accumulators is capable of supplying sufficient core cooling to limit peak cladding temperatures within acceptable limits for all postulated break sizes, from double-ended break of the largest RCS cold leg pipe downward. Each subsystem also provides long-term core cooling capability in the recirculation mode during accident recovery.

The ECCS flow paths ensure borated water delivery to both cold legs (injection phase) and hot legs (recirculation phase).

Pump runout limits: Surveillance requirements cap maximum total pump flow at 554 gpm for centrifugal charging pumps (accounting for suction boost alignment; 560 gpm nameplate), 664 gpm for SI pumps in cold leg alignment, and 654 gpm for SI pumps in hot leg alignment (675 gpm nameplate). The maximum–minimum flow surveillance ensures the minimum individual injection line resistance assumed for the spilling line following a LOCA is met.

Safety analysis assumptions: The safety analyses account for both maximum and minimum total system resistance and branch injection line resistance to calculate maximum and minimum ECCS flow bounds.

LCO 3.0.4.b restriction: LCO 3.0.4.b is not applicable to an inoperable ECCS high head subsystem when entering Mode 4. The provisions allowing entry into a Mode with the LCO not met after risk assessment should not be applied in this circumstance due to increased risk.

The RHR interlock (tested per SR 4.5.2.i) prevents opening the RHR suction isolation valves (2RH1, 2RH2) when RCS pressure is ≥375 psig, protecting the low-pressure RHR system from RCS pressure.


ECCS Subsystems — Tavg < 350°F

LCO 3.5.3
As a minimum, one ECCS subsystem shall be OPERABLE comprised of:
a. One centrifugal charging pump + flow path (cold leg injection)
b. One RHR pump + RHR HX + flow path (cold leg and hot leg injection)

Applicability: Mode 4

Actions:

ConditionRequired ActionCompletion Time
No ECCS subsystem (charging pump or flow path inoperable)Restore at least one1 hr, or Cold Shutdown in 20 hrs
No ECCS subsystem (RHR pump or HX inoperable)Restore or maintain Tavg <350°F by alternate heat removalImmediately
POPS Restriction
A maximum of one SI pump or one centrifugal charging pump shall be OPERABLE in Mode 4 (cold leg temp ≤ POPS enable temp), Mode 5, or Mode 6 (head on vessel). Excess pumps must be demonstrated inoperable by breaker removal or verified in recirc with two independent means of preventing RCS injection.

Amendment No. 328

▶ Bases — 3/4.5.3 ECCS Subsystems (Tavg < 350°F)
Bases — 3/4.5.3

With RCS temperature below 350°F, one OPERABLE ECCS subsystem is acceptable without single-failure consideration on the basis of the stable reactivity condition of the reactor and the limited core cooling requirements in Mode 4.

POPS basis: The limitation of a maximum of one SI pump or one centrifugal charging pump OPERABLE below the POPS enable temperature (specified in the PTLR) provides assurance that a mass addition pressure transient can be relieved by the operation of a single POPS relief valve.

Two independent means of preventing RCS injection are required when running an SI pump below the POPS enable temperature with potential for injecting into the RCS. Any two of the following satisfy this requirement:

  1. A manual isolation valve locked in the closed position
  2. Two manual isolation valves closed
  3. One motor-operated valve closed with breaker de-energized and control circuit fuses removed
  4. One air-operated valve closed with air supply maintained to ensure it remains closed

Seal Injection Flow

LCO 3.5.4
RCP seal injection flow shall be ≤40 gpm with charging pump discharge header pressure ≥2430 psig and charging flow control valve full open.

Applicability: Modes 1, 2, and 3

Action: Adjust manual seal injection throttle valves within 4 hrs, or Hot Standby in 6 hrs + Hot Shutdown in 6 hrs.

▶ Bases — 3/4.5.4 Seal Injection Flow
Bases — 3/4.5.4

RCP seal injection flow is restricted because it is NOT isolated during Safety Injection (SI) actuation — any flow diverted to the RCP seals is diverted from the ECCS injection path. The limit is therefore based on safety analysis assumptions for flow diversion.

The LCO is not strictly a flow limit but a flow limit based on line resistance: both line pressure and flow must be known to establish proper line resistance. The resistance is determined assuming RCS pressure at normal operating pressure and charging pump discharge pressure ≥ 2430 psig. Charging pump header pressure is used rather than RCS pressure because it is more representative of flow diversion during an accident. The charging flow control valve must be full open because it is designed to fail open.

Surveillance exemption: SR 4.0.4 is exempt for up to 4 hours after RCS pressure stabilizes within ±20 psig of normal operating pressure when entering Mode 3 — the exemption allows time to establish the conditions necessary to correctly set the manual throttle valves.

Exam -- 2023 Q91
Seal injection flow surveillance: individual RCP seal injection flows of 10 + 10.5 + 9.8 + 10.2 = 40.5 gpm total exceeds the ≤40 gpm limit. Required action: adjust manual seal injection throttle valves within 4 hours. This is NOT a charging pump operability issue (TS 3.5.2) -- the charging pump is functioning properly; the seal injection throttle valves need adjustment.

Refueling Water Storage Tank

LCO 3.5.5
The RWST shall be OPERABLE with:
a. Contained volume ≥ 364500 gallons
b. Boron concentration: 2300–2500 ppm
c. Temperature: ≥35°F and ≤100°F

Applicability: Modes 1, 2, 3, and 4

Actions:

ConditionRequired ActionCompletion Time
RWST inoperable (boron or temp)Restore8 hrs, or Hot Standby in 6 hrs + Cold Shutdown in 30 hrs
RWST inoperable (other reasons)Restore1 hr, or Hot Standby in 6 hrs + Cold Shutdown in 30 hrs

Amendment No. 309

▶ Bases — 3/4.5.5 RWST
Bases — 3/4.5.5

The RWST minimum volume and boron concentration limits ensure three things simultaneously:

  1. Sufficient water is available within containment to permit recirculation cooling flow to the core (the sump must have adequate inventory for long-term recirculation).
  2. The reactor will remain subcritical in the cold condition following a small LOCA, assuming complete mixing of RWST, RCS, and ECCS water volumes with all control rods inserted except the most reactive assembly (ARI-1 — stuck rod out).
  3. The reactor will remain subcritical in the cold condition following a large break LOCA (break flow area > 3.0 sq ft), assuming complete mixing with all control rods assumed out (ARO).

The boron concentration limits also ensure a post-LOCA sump pH between 7.0 and 10.0 for the solution recirculated within containment. This pH band minimizes iodine evolution and minimizes chloride and caustic stress corrosion on mechanical systems. The minimum volume limit includes an allowance for water not usable due to tank discharge line location or other physical characteristics.


View Tech Spec PDF | View Bases PDF

Exam — 2020 Q77
Loss of one centrifugal charging pump: TS 3.5.2 applies — one ECCS subsystem inoperable (the tripped CHP is the high-head component for that ECCS train). 72 hours to restore, then Hot Shutdown (MODE 4) within the next 12 hours (total 84 hours from the pump trip). The 23 Charging Pump (positive displacement) does NOT count as an ECCS high-head pump — it counts only for TS 3.1.2.4 (Charging Pumps for reactivity control). TS 3.1.2.2 (Boration Flow Paths) and TS 3.1.2.4 are NOT entered because two boration flow paths and two charging pumps (22 + 23) remain operable.
Exam — 2018 Q96
SR 4.5.2.b.2 (Verify that ECCS Piping Is Full Of Water) has a MONTHLY surveillance frequency. Per SR 4.0.3, the missed surveillance delay is 24 hours or the specified frequency (31 days), whichever is greatest = 31 days from discovery. A risk assessment is required for delays >24 hours.

Connections