Purpose

Administrative procedure governing Electric System Emergency Operations and Electric System Operator (ESO) Interface. Directs Station Load Curtailment actions when grid conditions require it.

Key Actions / Information

Exam — 2020 Q81
AB.GRID-0001 Attachment 3 directs initiating Station Load Curtailment IAW OP-AA-108-107-1001 when 500 KV Switchyard Voltage is < 493 KV on any line.