WC-AA-101 — On-Line Work Management Process

Purpose

Defines the process for managing on-line (at-power) maintenance activities, including roles and responsibilities for risk assessment, protected equipment, and FLEX capability.

Key Actions / Information

Exam — 2023 Q96
Shift Manager responsibilities for on-line maintenance (Step 3.6):
- 3.6.1: Ensures shift operations reassesses risk if an emergent condition results in a plant configuration not previously assessed
- 3.6.2: Ensures shift operations apply Protected Equipment barriers IAW OP-AA-108-116
- 3.6.3: Ensures fire risk management actions are implemented
- 3.6.4: Ensures the site FLEX capability is maintained
"Manages special or complex projects during on-line implementation" is NOT a SM responsibility — that belongs to the Online Maintenance Project Coordinator.