Q96 — Online Work Management / SM Responsibilities T3 G2.2.19 (3.4)
Per WC-AA-101, On-Line Work Management Process, which of the following choices are responsibilities of the Shift Manager in support of online maintenance?

1. Ensures site FLEX capability is maintained.
2. Ensures risk is reassessed when an emergent condition results in a plant configuration not previously assessed.
3. Ensures Protected Equipment barriers are applied per OP-AA-108-116, Protected Equipment Program.
4. Manages special or complex projects during on-line implementation.
A. 1, 2, 3, and 4
B. 1, 2, and 3 Only
C. 2 and 3 Only
D. 1 and 4 Only
▶ Show Answer & Explanation
✓ B. Correct. Per WC-AA-101, step 3.6, the Shift Manager responsibilities include the following: 3.6.1 Ensures shift operations reassesses risk if an emergent condition results in a plant configuration that has not been previously assessed, 3.6.2 Ensures shift operations apply Protected Equipment barriers IAW OP-AA-108-116, 3.6.3 Ensures fire in a(4) Risk Management Actions are implemented as applicable IAW the appropriate site specific procedure, 3.6.4 Ensures the site FLEX capability is maintained.
✗ A. Plausible because the SRO may believe that the SM has this responsibility based on the complex project. Incorrect in that per WC-AA-101, the responsibility belongs to the Online Maintenance Project Coordinator.
✗ C. Plausible because these are responsibilities of the SM. Incorrect in that choice 1 is also a responsibility of the SM.
✗ D. Plausible because choice 1 is a responsibility of the SM. Incorrect in that per WC-AA-101, the responsibility belongs to the Online Maintenance Project Coordinator.
Ref: WC-AA-101 (R30) | LO: NOS05WORK00-07, Objective 4. Describe the conditions under which the SM/CRS permission must be obtained prior to starting work, in accordance with WC-AA-10, Work Management Process Description, and WC-AA-101, On-Line Work Management Process. | Source: Modified - Byron 2017 NRC SRO96 | Cognitive: Fundamental/Memory