RCS
Function
The Reactor Coolant System (RCS) transfers heat generated in the reactor core to the steam generators, where steam is produced to drive the turbine-generator. The RCS provides a pressure boundary for containing coolant under operating temperature and pressure conditions, confines radioactive material, and limits releases to the secondary system and other parts of the plant. During transient operation, the system’s heat capacity attenuates thermal transients generated by the core or steam generators. (UFSAR 5.1)
System Configuration
- Type: Westinghouse 4-loop PWR
- Number of heat transfer loops: 4, connected in parallel to the reactor vessel
- Each loop contains: one steam generator, one reactor coolant pump, loop piping, and instrumentation
- Pressurizer surge line: connected to one loop (hot leg)
- All piping and fittings: austenitic stainless steel
- All joints: welded (except pressurizer relief and safety valves — flanged)
Key Design Parameters
| Parameter | Value | Source |
|---|
| Design Pressure | 2485 psig | UFSAR T5.1-1 |
| Nominal Operating Pressure | 2235 psig | UFSAR T5.1-1 |
| Design Temperature | 650°F | UFSAR T5.2-3 |
| Hydrostatic Test Pressure | 3107 psig | UFSAR T5.2-3 |
| Total Heat Output (100% power) | 11844 x 10⁶ Btu/hr | UFSAR T5.1-1 |
| Plant Design Life | 40 years | UFSAR T5.1-1 |
| Total System Volume (ambient), Unit 1 | 12071 ft³ | UFSAR T5.1-1 |
| Total System Volume (ambient), Unit 2 | 13011 ft³ | UFSAR T5.1-1 |
| System Liquid Volume (ambient), Unit 1 | 11351 ft³ | UFSAR T5.1-1 |
| System Liquid Volume (ambient), Unit 2 | 12291 ft³ | UFSAR T5.1-1 |
Reactor Coolant Temperatures (Full Power)
| Parameter | Unit 1 | Unit 2 | Source |
|---|
| Inlet Temp (High Tavg) | 542.7°F | 542.8°F | UFSAR T5.1-1 |
| Inlet Temp (Low Tavg) | 530.2°F | 530.3°F | UFSAR T5.1-1 |
| Outlet Temp (High Tavg) | 613.1°F | 613.1°F | UFSAR T5.1-1 |
| Outlet Temp (Low Tavg) | 601.8°F | 601.7°F | UFSAR T5.1-1 |
| Coolant Temp Rise (High Tavg) | 70.4°F | 70.3°F | UFSAR T5.1-1 |
| Coolant Temp Rise (Low Tavg) | 71.6°F | 71.4°F | UFSAR T5.1-1 |
Design Coolant Flow
| Parameter | Unit 1 | Unit 2 | Source |
|---|
| Total Design Flow (High Tavg) | 125.3 x 10⁶ lb/hr | 125.8 x 10⁶ lb/hr | UFSAR T5.1-1 |
| Total Design Flow (Low Tavg) | 127.3 x 10⁶ lb/hr | 125.9 x 10⁶ lb/hr | UFSAR T5.1-1 |
| Best Estimate Flow per Loop, Unit 1 | 94200 gpm | — | UFSAR T5.2-2 |
| Best Estimate Flow per Loop, Unit 2 | 94800 gpm | — | UFSAR T5.2-2 |
Pressure Control Setpoints
| Parameter | Value (psig) | Source |
|---|
| Design Pressure | 2485 | UFSAR T5.2-1 |
| Operating Pressure | 2235 | UFSAR T5.2-1 |
| Safety Valves (lift) | 2485 | UFSAR T5.2-1 |
| PORVs (lift / reset) | 2335 / 2315 | UFSAR T5.2-1, T5.2-8 |
| High Pressure Trip | 2385 | UFSAR T5.2-1 |
| High Pressure Alarm | 2385 | UFSAR T5.2-1 |
| Low Pressure Trip | 1865 | UFSAR T5.2-1 |
| Low Pressure Alarm | 1865 | UFSAR T5.2-1 |
| Pressurizer Spray (begin to open) | 2260 | UFSAR T5.2-1 |
| Pressurizer Spray (full open) | 2310 | UFSAR T5.2-1 |
| Proportional Heaters (begin) | 2250 | UFSAR T5.2-1 |
| Proportional Heaters (full operation) | 2220 | UFSAR T5.2-1 |
| Backup Heaters On | 2210 | UFSAR T5.2-1 |
| Hydrostatic Test Pressure | 3107 | UFSAR T5.2-1 |
Key Components
- Rx Vessel & Internals: Cylindrical vessel with hemispherical heads, contains core and internals. 4 inlet/4 outlet nozzles. (UFSAR 5.1, 5.4)
- Pressurizer & PRT: Vertical cylindrical vessel, 84” ID. Maintains liquid-vapor equilibrium for pressure control. 1800 kW heaters, 800 gpm max spray. Connected to one hot leg via 14” surge line. (UFSAR 5.1, T5.2-4)
- Steam Generator & Blowdown: 4 vertical shell and U-tube evaporators with integral moisture separation. Unit 1: Model F (5626 U-tubes, Inconel). Unit 2: AREVA NP Model 61/19T (5048 U-tubes, Inconel 690 TT). (UFSAR 5.1, T5.2-5)
- RCPs: 4 vertical single-stage mixed-flow pumps, Model 93A. 6000 HP motors, 88500 gpm capacity, 277 ft developed head, 1180 RPM. Controlled leakage seal assembly. (UFSAR 5.1, T5.2-6)
- Pressurizer Relief Tank: Carbon steel, 1800 ft³ total volume. Design pressure 100 psig. Two rupture discs (100 psig) discharge to containment. Normal water temperature at containment ambient (120°F max). (UFSAR 5.1, T5.2-4)
RCS Piping
| Parameter | Value | Source |
|---|
| Reactor Inlet (Cold Leg) ID | 27.5 in | UFSAR T5.2-7 |
| Reactor Outlet (Hot Leg) ID | 29 in | UFSAR T5.2-7 |
| Pump Suction Piping ID | 31 in | UFSAR T5.2-7 |
| Surge Line ID, Unit 1 | 11.500 in | UFSAR T5.2-7 |
| Surge Line ID, Unit 2 | 11.188 in | UFSAR T5.2-7 |
| Total Water Volume (all 4 loops + surge line) | 1455 ft³ | UFSAR T5.2-7 |
Pressure Relief
- Safety Valves: 3 per unit, Crosby HB-BP-86, set at 2485 psig, rated capacity 420000 lb/hr each (saturated steam). 6” inlet x 6” outlet. (UFSAR T5.2-8)
- PORVs: 2 per unit, Copes-Vulcan diaphragm-operated, set at 2335 psig (reset 2315 psig), rated capacity 210000 lb/hr each. 2” valve with 3” connections. (UFSAR T5.2-8)
- PORV Block Valves: 2 per unit, Velan 3” motor-operated gate valves with Limitorque operators. (UFSAR T5.2-8)
- All safety/relief valves discharge to the pressurizer relief tank.
RCS Pressure Drop
| Leg | Unit 1 (psi) | Unit 2 (psi) | Source |
|---|
| Pump Discharge Leg | 3.1 | 3.1 | UFSAR T5.2-2 |
| Across Vessel (incl. nozzles) | 49.3 | 49.3 | UFSAR T5.2-2 |
| Hot Leg | 1.1 | 1.2 | UFSAR T5.2-2 |
| Across Steam Generator | 35.8 | 34.4 | UFSAR T5.2-2 |
| Pump Suction Leg | 2.9 | 2.9 | UFSAR T5.2-2 |
| Total | 92.2 | 90.9 | UFSAR T5.2-2 |
RCS High Point Venting
Three principal high points: pressurizer, reactor vessel head, and steam generator tube bundle invert.
- Pressurizer vent: PORV serves as safety-grade vent, operable from control room, meets single failure criterion.
- Reactor vessel head vent: Dedicated ¾” Schedule 160 vent tap with 3/8” restricting orifice. Vents to PRT or containment via redundant solenoid valves. Remote-manually actuated from control room via key lock switch. Powered from two redundant vital DC buses. Designed to NUREG-0737 requirements. Vent size within LOCA definition (3/8” orifice) — inadvertent opening does not require ECCS actuation. Can vent ½ gas volume of RCS in 1 hour. (UFSAR 5.1)
- Steam generator tube invert: Cannot be vented at that location. Westinghouse study (WCAP-9600/9601) concluded small amount of noncondensables would not significantly impact natural circulation.
Exam — 2023 Q17
During RCS depressurization without RCPs running (e.g., EOP-LOCA-5),
upper head voiding IS expected. Without forced circulation, the upper head contains hotter liquid that
flashes to steam during depressurization, displacing water into the pressurizer and causing a
rapidly rising PZR level. Monitor PZR level to stop depressurization before going solid.
Tech Spec LCOs
- TS 3/4.4 — Reactor Coolant System — RCS pressure, temperature, flow limits
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.1 — Reactor Coolant Loops (Modes 1-4)
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.2 — Safety Valves
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.3 — PORVs and Block Valves
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.4 — Pressurizer
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.5 — Steam Generators
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.6 — RCS Leakage Detection
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.7 — RCS Leakage
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.8 — Chemistry
- TS 3/4.4 — Reactor Coolant System|TS 3/4.4.9 — Specific Activity
JPM — 2023 Sim-d
EOP-FRHS-1 Bleed and Feed: actuate SI, open PZR PORVs. If 2PR2 fails to open, open
reactor head vent valves 2RC40 through 2RC43 (key-locked on 2RP2 backpanel) as alternate bleed path. Requires going to backpanel to insert key and turn each valve individually.
Thermal-Hydraulic Design
Function
The thermal-hydraulic design ensures adequate heat transfer between the fuel cladding and reactor coolant so the core thermal output is not limited by fuel temperature or DNB considerations. The design takes into account local variations in fuel rod dimensions, power generation, flow distribution, and mixing. (UFSAR 4.4)
Core Thermal Parameters
| Parameter | Value | Source |
|---|
| Reactor Core Heat Output | 3459 MWt | UFSAR T4.4-1 |
| Reactor Core Heat Output, Unit 1 | 11806 x 10⁶ Btu/hr | UFSAR T4.4-1 |
| Reactor Core Heat Output, Unit 2 | 11844 x 10⁶ Btu/hr | UFSAR T4.4-1 |
| Heat Generated in Fuel | 97.4% | UFSAR T4.4-1 |
| Nominal System Pressure | 2250 psia | UFSAR T4.4-1 |
| Minimum Steady State Pressure (STDP) | 2218 psia | UFSAR T4.4-1 |
Coolant Flow
| Parameter | Value | Source |
|---|
| Total Thermal Design Flow Rate | 125.3 x 10⁶ lb/hr | UFSAR T4.4-1 |
| Effective Flow Rate (Unit 1) | 116.3 x 10⁶ lb/hr | UFSAR T4.4-1 |
| Effective Flow Rate (Unit 2) | 115.7 x 10⁶ lb/hr | UFSAR T4.4-1 |
| Effective Flow Area (V5H, V+) | 51.3 ft² | UFSAR T4.4-1 |
| Effective Flow Area (RFA) | 51.1 ft² | UFSAR T4.4-1 |
| Average Velocity Along Fuel Rods (V5H, V+) | 14.1 ft/sec | UFSAR T4.4-1 |
| Average Velocity Along Fuel Rods (RFA) | 14.2 ft/sec | UFSAR T4.4-1 |
| Average Mass Velocity (V5H, V+) | 2.27 x 10⁶ lb/hr-ft² | UFSAR T4.4-1 |
| Average Mass Velocity (RFA) | 2.28 x 10⁶ lb/hr-ft² | UFSAR T4.4-1 |
Coolant Temperatures
| Parameter | Value | Source |
|---|
| Nominal Inlet Temperature | 542.7°F | UFSAR T4.4-1 |
| Average Rise in Vessel | 70.4°F | UFSAR T4.4-1 |
| Average Rise in Core | 75.2°F | UFSAR T4.4-1 |
| Average in Core (Unit 1) | 582.4°F | UFSAR T4.4-1 |
| Average in Core (Unit 2) | 582.6°F | UFSAR T4.4-1 |
| Average in Vessel | 577.9°F | UFSAR T4.4-1 |
Heat Transfer
| Parameter | Value | Source |
|---|
| Active Heat Transfer Surface Area | 59700 ft² | UFSAR T4.4-1 |
| Average Heat Flux | 192470 Btu/hr-ft² | UFSAR T4.4-1 |
| Maximum Heat Flux (normal operation) | 461930 Btu/hr-ft² | UFSAR T4.4-1 |
| Average Thermal Output | 5.52 kW/ft | UFSAR T4.4-1 |
| Maximum Thermal Output (normal operation) | 13.3 kW/ft | UFSAR T4.4-1 |
| Peak Linear Power (protection setpoints) | ≤22.4 kW/ft | UFSAR T4.4-1 |
| Peak Fuel Center Temp (max overpower trip) | <4700°F | UFSAR T4.4-1 |
| Heat Flux Hot Channel Factor (FQ) | 2.40 | UFSAR T4.4-1 |
| Fuel Clad Outer Surface Temp (hot spot, steady state) | ~660°F | UFSAR 4.4.2.2.5 |
Core Pressure Drop
| Configuration | Pressure Drop (psi) | Source |
|---|
| Full core V5H, V+ | 22.2 | UFSAR T4.4-1 |
| Full core RFA with DFBN | 24.7 | UFSAR T4.4-1 |
| Full core RFA with SDFBN | 24.5 | UFSAR T4.4-1 |
Based on best estimate flow of 93300 gpm/loop (DFBN) or 94800 gpm/loop (SDFBN). (UFSAR T4.4-1)
Departure from Nucleate Boiling (DNB)
DNBR Design Limits
| Fuel Type | Cell Type | DNBR Design Limit | Correlation | Source |
|---|
| V5H, V+ | Typical | 1.24 (RTDP) | WRB-1 | UFSAR T4.4-1 |
| V5H, V+ | Thimble | 1.24 (RTDP) | WRB-1 | UFSAR T4.4-1 |
| RFA | Typical | 1.24 (RTDP) | WRB-2 | UFSAR T4.4-1 |
| RFA | Thimble | 1.22 (RTDP) | WRB-2 | UFSAR T4.4-1 |
DNBR correlation limit: 1.17 for both WRB-1 and WRB-2. (UFSAR T4.4-1)
DNBR at Normal Conditions
| Fuel Type | Cell Type | DNBR | Source |
|---|
| V5H, V+ | Typical | 2.44 | UFSAR T4.4-1 |
| V5H, V+ | Thimble | 2.32 | UFSAR T4.4-1 |
| RFA | Typical | 2.64 | UFSAR T4.4-1 |
| RFA | Thimble | 2.62 | UFSAR T4.4-1 |
Design Basis
The design basis for DNB is that there is at least a 95% probability at the 95% confidence level that the limiting fuel rod in the core does not experience DNB during Condition I and II events. This is met by ensuring the minimum DNBR remains above the design limit DNBR. (UFSAR 4.4.1.1)
RTDP (Revised Thermal Design Procedure): Plant operating parameter uncertainties (pressure, temperature, power, flow) are statistically combined into the DNBR design limit, allowing safety analyses to use nominal values. (UFSAR 4.4.1.1)
STDP (Standard Thermal Design Procedure): Used when RTDP is not applicable. Minimum steady state pressure of 2218 psia is assumed. (UFSAR T4.4-1)
Key Exam Concepts
- DNB = transition from nucleate boiling to film boiling on fuel rod surface; results in rapid temperature increase
- DNBR = ratio of heat flux required to cause DNB to actual local heat flux; must stay above design limit
- The fuel design basis is that centerline fuel melt does not occur during normal operation or AOOs
- Core average void fraction is less than 0.5% (due to local/statistical boiling only)
- RFA fuel has higher DNBR margins than V5H fuel (better mixing from IFM grids)
Thermal-Hydraulic Tech Spec LCOs
- TS 3/4.2.1 — Axial Flux Difference (delta-I)
- TS 3/4.2.2 — Heat Flux Hot Channel Factor (FQ)
- TS 3/4.2.3 — Nuclear Enthalpy Rise Hot Channel Factor (F-delta-H)
- TS 3/4.2.5 — DNB Parameters (pressurizer pressure, RCS Tavg, RCS flow)
Exam — 2023 Q73
Steam table subcooling calculation: at
1805 psig (1820 psia), RCS Tsat = 623°F. For 100°F subcooling margin, cold leg temperature must be ≤523°F. Since SGs are saturated and negligible delta-T exists across SG tubes, SG temperature must also be ~523°F.
Saturation pressure at 523°F is approximately 820 psia (805 psig).
Common trap: failing to convert psia to psig (off by ~15 psi).
Exam — 2023 Q74
Condensate depression effects: decreasing condensate depression (from 5°F to 2°F) means the condensate is
closer to saturation temperature. This produces
less NPSH at the condensate pump suction (closer to cavitation) because there is less subcooling to prevent flashing. However, because the feedwater is hotter, the SGs must add
less sensible heat to reach saturation — improving steam cycle thermal efficiency.
Trap: lower condensate depression means higher efficiency but worse pump cavitation margin — effects go in opposite directions.
JPM — 2018 Sim-d
EOP-FRHS-1 Bleed and Feed (Steps 21-25): loss of all AFW, 3 SG WR levels < 32% → Bleed and Feed criteria met. Initiate SI on both trains. Verify charging/SI pumps running, BIT flow ~150-160 gpm, Table C valves open. Open both PORV stop valves (2PR6, 2PR7). Open both PORVs in Manual —
2PR2 fails to open (alternate path). At
2RP2 backpanel, use four keys to open reactor head vent valves 2RC40 through 2RC43 as alternate bleed path.
Reactor Head Vents are NOT the standard bleed path — only used when a PORV fails to open.
JPM — 2022 RO-A1
EOP-FRCI-3 Attachment 1 maximum vent time calculation for reactor vessel upper head voiding: at
1600 psig RCS pressure, hydrogen flow rate from Figure 1 is
3333 cfm. Maximum containment hydrogen increase limited to keep total below
3.0%. With 2.3% current H2 and 140F containment temperature, maximum vent time =
4.5 minutes.
Exam — 2019 Q69
Subcooling calculation when subcooling monitor is NOT functional: convert
psig to PSIA by adding 14.7 (rounded to 15), use steam tables to find TSAT. Subcooling = TSAT -
Hottest CET (not TAVG).
Two traps: (1) subtracting 15 instead of adding gives wrong TSAT, (2) using TAVG instead of Hottest CET gives wrong subcooling. Hottest CET is always the correct reference for subcooling calculation.
JPM — 2018 RO-A2
Control room log OTDT setpoint channel check: each RC loop's OTDT console reading compared against REM FIGURE 5 (A-D) setpoint band. Tavg Channel Check requires all 4 loop average temperatures within
3 degrees F (S/R 4.3.2.1.1, Modes 1-3). Loop 24 OTDT of 72 deg F found
outside the REM FIGURE 5D setpoint band.
Connections
- Pressure boundary code: ASME Section III (UFSAR 5.2.1.3)
- Related EOPs: EOP-FRHS-1 — Response to Loss of Secondary Heat Sink, EOP-FRCI-3 — Response to Void in Reactor Vessel
- Related procedures: S2.OP-DL.ZZ-0003 — Control Room Logs
- Related exam questions: 2018 Q3, 2018 Q63, 2018 Q65, 2018 Q70, 2019 Q69, 2020 Q16, 2020 Q17, 2020 Q18, 2023 Q17, 2023 Q73, 2023 Q74
- Related JPMs: 2018 JPM RO-A2, 2018 JPM Sim-d, 2023 JPM Sim-d, 2022 JPM RO-A1
- Related scenarios: 2018 Scenario 1, 2018 Scenario 2, 2019 Scenario 1 — Power Ascension / LOCA Outside Containment, 2019 Scenario 3 — ATWS / Stuck-Open PORV, 2019 Scenario 4 — SGFP Trip / Loss of Heat Sink, 2022 Scenario 3 — Power Ascension / Loss of Heat Sink
- Related exam: 2018 NRC Operating Exam, 2019 NRC Written Exam, 2019 NRC Operating Exam, 2020 NRC Written Exam, 2023 NRC Written Exam, 2023 NRC Operating Exam, 2022 NRC Operating Exam