Exams > 2018 JPM Sim-e — Synchronize the Main Generator

2018 JPM Sim-e — Synchronize the Main Generator

⚠️ DRAFT
JPM Sim-e — Synchronize the Main Generator Sim | RO/SRO | 045 A4.02 (2.7/2.6)
Location: Simulator
Time-Critical: No
Alternate Path: No
Estimated Time: 18 minutes

Initial Conditions:
- Unit 2 is at 16% power starting up from a maintenance outage.
- The crew is performing power ascension activities IAW S2.OP-IO.ZZ-0003, Hot Standby to Minimum Load.
- The main turbine is at 1800 rpm with generator excitation applied.

Initiating Cue:
- You are the Plant Operator.
- The CRS has directed you to synchronize the Generator IAW S2.OP-SO.TRB-0001, Turbine-Generator Startup Operations, Section 4.5, Synchronizing the Generator.
- All Prerequisites are completed SAT.
- Step 4.5.1 IVs are completed SAT.
- Synchronize the Generator starting at Step 4.5.2. The 500 KV 1-9 breaker will be closed first followed by the 500 KV 9-10 breaker.
Task Standard:
Synchronizes the Generator to the electrical grid IAW S2.OP-SO.TRB-0001.
▶ Show Critical Steps & Key Actions
Step Critical Element Standard
4.5.2 Ensure 500 KV BUS SECT 9-10 (30X) Breaker selected to 9-10 LOCAL Verifies 9-10 Breaker is selected to 9-10 LOCAL.
4.5.3 Select No. 2 Unit Scope Transfer Switch to REGULAR or SPARE SCOPE Verifies REGULAR SCOPE is illuminated on 2RP6.
4.5.4 Scope test — verify synchroscope and voltmeters respond Presses SCOPE TEST pushbutton on 500KV Breaker Sections 1-9 (32X). Verifies synchroscope hand at 12 o'clock. Verifies INCOM KV and RUN KV voltmeters move upscale. Releases SCOPE TEST PB.
4.5.5 Verify MAIN GEN SYNC PERM BYPASS keylock switch in NORMAL Verifies MAIN GEN SYNC PERM BYPASS keylock switch is in NORMAL position.
4.5.6 * Select 1-9 Mimic Bus and 1-9 SYNCH POT ON Depresses 1-9 Mimic Bus PB and verifies yellow backlight AND console bezel for MIMIC BUS 1-9 INTERLOCK CLOSE SELECTION is illuminated. Depresses 1-9 SYNCH POT ON and verifies bezel illuminates.
4.5.8 * Adjust INCOM KV to 3-5 KV greater than RUN KV using Voltage Regulator Determines INCOM KV is NOT 3-5 KV greater than RUN KV (as-found: INCOM KV ~499, RUN KV ~498). At EXCITATION, VOLTAGE REGULATOR, VREG CNTRL SETPT ADJ, depresses RAISE SETPT until INCOM KV is 3-5 KV greater than RUN KV (at least 501 KV to meet Synch Permissive).
4.5.12.1 * Adjust turbine speed until synchroscope rotates SLOWLY in FAST direction (~1 revolution every 25-30 seconds) Determines turbine speed adjustment required. Adjusts SETTER 1-2 rpm above reference (as-found: SETTER = 1801, raise to 1802-1803). Selects SETTER GO (illuminates green). Verifies ACTUAL and REFERENCE speed adjust to SETTER speed. Synchroscope rotates slowly in FAST direction.
4.5.12.3 * Close 500KV 1-9 (32X) breaker when synchroscope is 1-2 minutes before 12 o'clock Depresses CLOSE PB for 500 KV GROUP BUS BREAKER Section 1-9 (32X) when synchroscope is 1-2 minutes before 12 o'clock. Verifies 1-9 CLOSE PB is illuminated. Verifies load is rising (MW indicator on 2RP3, MW Recorder on 2RP5, or HMI panel).
4.5.12.4 Verify generator load rises to 40-60 MW within 15 seconds Verifies generator load rises to 40-60 MW within 15 seconds. If not, raises SETTER <= 4% above REFERENCE and selects GO.
4.5.12.5 Select SYNCH POT OFF for 1-9 breaker Depresses SYNCH POT OFF PB and verifies bezel illuminates.
Key Decision Point:
Two discriminating elements in this JPM. First (Step 4.5.8): the applicant must recognize that INCOMING voltage is NOT 3-5 KV above RUNNING voltage (as-found both ~498-499 KV) and use the Voltage Regulator RAISE SETPT to increase INCOM KV to at least 501 KV — this satisfies one of the Synch Permissive requirements. Second (Step 4.5.12.1): the turbine is initially rotating too slowly (SETTER = 1801 rpm, producing slow FAST rotation). The applicant must increase the SETTER by 1-2 rpm increments and select SETTER GO to achieve a synchroscope rotation of approximately one revolution every 25-30 seconds in the FAST direction. Failing to satisfy either condition will prevent the MAIN GEN SYNC PERMISSIVE light from illuminating.
Ref: S2.OP-SO.TRB-0001 (Rev 47) | Task: N0450040101 | K/A: 045 A4.02 — Ability to manually operate and/or monitor in the control room: Main Turbine Generator (2.7/2.6) | Source: Modified | View JPM PDF