Q52 — CVCS Charging Line Leak
APE: 022 Loss of Rx Coolant Makeup-AA2.01 (3.2)
Given:
• Unit 2 is at 100% Reactor Power and stable
At time 16:00:00
• 2R41 (Plant Radiation Monitor) reading is trending up
• PZR Level is lowering
• Seal Injection flow is lowering
• Letdown line flashing is occurring
At 16:00:00, which ONE of the following completes the statements below?
There is a leak on the CVCS _(1)_ line.
S2.OP-AB.CVC-0001 (Loss Of Charging) entry conditions _(2)_ met.
• Unit 2 is at 100% Reactor Power and stable
At time 16:00:00
• 2R41 (Plant Radiation Monitor) reading is trending up
• PZR Level is lowering
• Seal Injection flow is lowering
• Letdown line flashing is occurring
At 16:00:00, which ONE of the following completes the statements below?
There is a leak on the CVCS _(1)_ line.
S2.OP-AB.CVC-0001 (Loss Of Charging) entry conditions _(2)_ met.
A. _(1)_ letdown / _(2)_ are
B. _(1)_ letdown / _(2)_ are NOT
C. _(1)_ charging / _(2)_ are
D. _(1)_ charging / _(2)_ are NOT
▶ Show Answer & Explanation
✓ C. Correct. For Part 1, based on the question stem conditions, there is a leak on the CVCS charging line (seal injection lowering, PZR level lowering, Plant Radiation Monitor rising, and flashing in the letdown line). For Part 2, a leak in the charging supply line is an entry condition for S2.OP-AB.CVC-0001.
✗ A. Incorrect but plausible. For Part 1, many of the indications given are also indicative of a letdown line leak (PZR level lowering and Plant Radiation Monitor rising). Consequently, the candidate could incorrectly conclude that a leak on the CVCS letdown line exists. For Part 2, the candidate could incorrectly conclude that a leak on the letdown would ultimately affect charging flow rate. A reduction in charging flow is an entry condition to S2.OP-AB.CVC-0001.
✗ B. Incorrect but plausible. For Part 1, many of the indications given are also indicative of a letdown line leak (PZR level lowering and Plant Radiation Monitor rising). Consequently, the candidate could incorrectly conclude that a leak on the CVCS letdown line exists. For Part 2, a leak on the letdown line is not an entry condition to S2.OP-AB.CVC-0001.
✗ D. Incorrect but plausible. Part 1 is correct. For Part 2, since RCS inventory is being lost, the candidate could incorrectly conclude that only entry conditions to S2.OP-AB.RC-0001 (Reactor Coolant System Leak) are met. Additionally, since the charging pump is providing flow to seal injection and the regenerative heat exchanger, the candidate could also incorrectly conclude S2.OP-AB.CVC-0001 entry conditions are not met.
Ref: S2.OP-AB.CVC-0001 (Loss Of Charging) | LO: NOS05ABRCP0-06 | Source: New | Cognitive: Higher