Exams > 2018 Q84 — Loss of RHR / Containment Closure

2018 Q84 — Loss of RHR / Containment Closure

⚠️ DRAFT
Q84 — Loss of RHR / Containment Closure APE: 069 Loss of Containment Integrity-G2.4.6 (4.7)
Given:
• A Core offload has just begun
• A loss of RHR has occurred
• The crew is performing S2.OP-AB.RHR-0001 (Loss Of RHR) and S2.OP-AB.CONT-0001 (Containment Closure)
• The Outage Equipment Hatch is currently open

In accordance with S2.OP-AB.CONT-0001, which ONE of the following completes the statements below?

S2.OP-AB.CONT-0001 states that Containment Closure should be established _(1)_.

S2.OP-AB.CONT-0001 states that the crew may close the Outage Equipment Hatch using a MINIMUM of _(2)_.

NOTE:
• SC.MD-FR.CAN-0001 (Outage Equipment Hatch Installation, Removal, Seal Replacement And Door Manipulation For Containment Closure)
A. _(1)_ prior to Core Boiling    _(2)_ 10 bolts per SC.MD-FR.CAN-0001
B. _(1)_ prior to Core Boiling    _(2)_ 4 corner bolts per S2.OP-AB.CONT-0001
C. _(1)_ within a MAXIMUM of four hours    _(2)_ 10 bolts per SC.MD-FR.CAN-0001
D. _(1)_ within a MAXIMUM of four hours    _(2)_ 4 corner bolts per S2.OP-AB.CONT-0001
▶ Show Answer & Explanation
✓ B. Correct. For Part 1, S2.OP-AB.CONT-0001 states that for a loss of RHR, Containment Closure should be established prior to Core Boiling. For Part 2, S2.OP-AB.CONT-0001 states that for a loss of RHR, the Outage Equipment Hatch may be closed using 4 corner bolts.
✗ A. Part 1 is correct. For Part 2, if the reason for entering S2.OP-AB.CONT-0001 was due to something other than Loss of RHR, then the crew would install the Outage Equipment Hatch (using ALL 10 bolts) by using the guidance contained in SC.MD-FR.CAN-0001. Consequently, the candidate could incorrectly conclude that with a loss of RHR in progress, the crew will install the Outage Equipment Hatch for Containment Closure by using the guidance contained in SC.MD-FR.CAN-0001.
✗ C. For Part 1, S2.OP-AB.CONT-0001 states that when the initiating event is other than a Fuel Handling Incident or Loss Of RHR, Containment Closure should be established within four hours. Additionally, with the cavity flooded, time to boil on a Loss of RHR can be several hours. Consequently, the candidate could incorrectly conclude that with a Loss of RHR in progress and the cavity flooded, S2.OP-AB.CONT-0001 states that Containment Closure should be established within a MAXIMUM of four hours. For Part 2, if the reason for entering S2.OP-AB.CONT-0001 was due to something other than Loss of RHR, then the crew would install the Outage Equipment Hatch (using ALL 10 bolts) by using the guidance contained in SC.MD-FR.CAN-0001.
✗ D. For Part 1, S2.OP-AB.CONT-0001 states that when the initiating event is other than a Fuel Handling Incident or Loss Of RHR, Containment Closure should be established within four hours. Part 2 is correct.
Ref: S2.OP-AB.CONT-0001 | LO: NOS05ABCONT-07 (CONTAINMENT CLOSURE) — 2. Describe, in general terms, the actions taken in S1/S2.OP-AB.CONT-0001 (Q) and the bases for the actions in accordance with the Technical Bases Document | Source: New | Cognitive: Higher