Exams > 2020 JPM IP-k — Place 11 CVCS Monitor Tank in Recirculation IAW S1.OP-SO.WL-0001

2020 JPM IP-k — Place 11 CVCS Monitor Tank in Recirculation IAW S1.OP-SO.WL-0001

⚠️ DRAFT
JPM IP-k — Place 11 CVCS Monitor Tank in Recirculation IAW S1.OP-SO.WL-0001 In-Plant (RCA) | RO/SRO | 068 A2.02 (2.7/2.8)
Location: In-Plant — Unit 1 RCA
Time-Critical: No
Alternate Path: No
Estimated Time: 25 minutes

Initial Conditions:
- The 11 CVCS Monitor Tank is at 90% and processing for release is being performed.

Initiating Cue:
- You are the extra NCO.
- The CRS directs you to place 11 CVCS Monitor Tank in recirculation using section 5.1 of S1.OP-SO.WL-0001, Release of Radioactive Liquid Waste from 11 CVCS Monitor Tank.
- 11 Monitor Tank Pump will be placed in service.
Task Standard:
1. Correctly performs recirculation valve lineup using Attachment 1 IAW S1.OP-SO.WL-0001
2. Correctly determines minimum recirculation time of 6 Hrs 30 Mins (band 6 Hrs 20 Mins to 6 Hrs 40 Mins)
▶ Show Critical Steps & Key Actions
Step Critical Element Standard
NOTE Any additions made to Monitor Tank that is isolated and placed on recirculation for sampling will invalidate sample analysis, requiring further recirculation time and additional sampling. Operator reads note and continues.
5.1.1 * PLACE valves in "Recirc Position" IAW Attachment 1, Section 1.0 Correctly locates and re-positions each valve IAW Attachment 1: 11WR27 MT PMP SUCT V — OPEN; 11WR31 MT PMP DISCH V — OPEN; 12WR27 MT PMP SUCT V — CLOSED; 12WR31 MT PMP DISCH V — CLOSED.
5.1.2 DIRECT second Operator to PERFORM Independent Verification IAW Attachment 1, Section 1.0 Directs IV. CUE: IVs are complete.
5.1.3 PLACE LO-LEVEL CUT-OFF switch in TANK 11 position Operator places LO-LEVEL CUT-OFF switch in the TANK 11 position.
5.1.4 * IF recirculating 11 CVCS MT with 11 MT Pump, THEN START 11 MT Pump Operator starts 11 MT Pump by depressing start pushbutton.
5.1.5 IF recirculating 11 CVCS MT with 12 MT Pump, THEN START 12 MT Pump Operator marks step as N/A (using 11 MT Pump per cue).
5.1.6 * THROTTLE 11WR53, MT RECIRC V, to maintain 80 psig on discharge of operating MT Pump Throttles 11WR53 in the closed (clockwise) direction to raise discharge pressure from 40 psig to 80 psig.
5.1.7 * COMPLETE Attachment 1, Section 2.0 — determine tank volume and minimum recirculation time Records current time as start time (A). Records tank level = 90%. Refers to S1.OP-TM.ZZ-0002 (CVCS Monitor Tank curve, Page 8) and determines tank volume = 19500 gallons (acceptable band 19000 to 20000). Calculates minimum recirculation time: (Volume x 3) / 150 gpm = 6 Hrs 30 Min (acceptable band: 6 Hrs 20 Min to 6 Hrs 40 Min). Adds time (B) to start time (A) for completion time.
5.1.8 DIRECT second Operator to PERFORM Independent Verification of calculations in Attachment 1, Section 2.0 Directs IV of calculations. CUE: IV is complete.
Key Decision Point:
Step 5.1.7 is the discriminating step — the applicant must correctly interpret the CVCS Monitor Tank capacity curve from S1.OP-TM.ZZ-0002 to convert 90% tank level to approximately 19500 gallons, then correctly apply the recirculation time formula: (Volume x 3) / 150 gpm. Incorrect curve reading or calculation error will yield a wrong minimum recirculation time. The formula requires multiplying volume by 3 (three tank volume turnovers) and dividing by the 150 gpm pump flow rate.
Ref: S1.OP-SO.WL-0001 (R28) | Task: N0680010101 | K/A: 068 A2.02 — Ability to (a) predict the impacts of malfunctions or operations on the Liquid Radwaste System; and (b) use procedures to correct, control, or mitigate: Lack of tank recirculation prior to release | Source: New | View JPM PDF