Exams > 2020 JPM Sim-a — Failed Open PZR Spray Valve

2020 JPM Sim-a — Failed Open PZR Spray Valve

⚠️ DRAFT
JPM Sim-a — Failed Open PZR Spray Valve Sim | RO/SRO | 010 A4.01 (3.7/3.5)
Location: Simulator
Time-Critical: No
Alternate Path: Yes
Estimated Time: 5 minutes

Initial Conditions:
- The Unit 2 is operating at 100% power with no major equipment out of service.

Initiating Cue:
- You are the Reactor Operator.
- Respond to all indications and alarms.
- Your evaluator will respond to all alarms not related to your task.
Task Standard:
Stops the RCS pressure decrease by closing 2PS1, or Trips the Reactor and stops 21 and 23 RCPs, before an Automatic SI occurs.
▶ Show Critical Steps & Key Actions
Step Critical Element Standard
Observe Recognize PZR Pressure Channel 1 failed high Scans control board; recognizes PZR Pressure Channel 1 is failed high. OHA D-8 (RC PRESS HI), OHA E-42 (2PR1 1/2 TRIP) annunciate.
MPC * Place Master Pressure Controller in MANUAL Depresses the MANUAL pushbutton for the Master Pressure Controller (MPC).
MPC * LOWER demand on MPC to close spray valves Depresses the PRESS INC pushbutton on the MPC to lower the demand.
Alt * Recognize 2PS1 is fully OPEN after MPC demand is zeroed With MPC demand at zero, operator reports 2PS1 remains fully OPEN. Alternate Path starts here.
3.18 * Place 2PS1 in MANUAL and CLOSE Depresses MANUAL pushbutton for 2PS1, then depresses the CLOSE pushbutton. 2PS1 valve demand lowers and open light extinguishes.
3.19 * OPERATE Spray Valves to control pressure per Attachment 2 Depresses CLOSE PB for 2PS1; recognizes 2PS1 demand is lowering and open light extinguished. Reports 2PS1 is CLOSED and RCS pressure is stable or rising.
Key Decision Point:
The alternate path / discriminating step occurs when the operator lowers MPC demand to close both spray valves but 2PS1 remains fully open. The applicant must recognize the stuck-open spray valve, place 2PS1 in manual, and close it directly. If the operator enters AB.PZR-0001 first rather than taking immediate action, the procedure leads through Steps 3.3 (identify failed channel), 3.5 (MPC to Manual), 3.6 (adjust MPC), then to 3.17/3.18/3.19 for the failed spray valve. Both paths are acceptable. Alternate task standard: if RCS pressure drops to 2000 psig and continues to drop, trip the reactor and stop 21 and 23 RCPs (spray is fed from Loops 1 and 3 cold legs).
Ref: S2.OP-AB.PZR-0001 (R18) | Task: 1140240401 | K/A: 010 A4.01 — Ability to predict impacts of PZR spray valve malfunction and use procedures to mitigate | Source: Modified | View JPM PDF