JPM Sim-c — Depressurize RCS Using Aux Spray IAW EOP-LOCA-2
Sim | RO/SRO | A4.05 (3.2)
Location: Simulator
Time-Critical: No
Alternate Path: Yes
Estimated Time: 5 minutes
Initial Conditions:
- The reactor was tripped when a RCS leak occurred.
- All RCPs have been stopped
- 2PR1 is inoperable with 2PR6 isolated with power removed
- The operating crew has progressed through the EOPs and is now in 2-EOP-LOCA-2, POST LOCA COOLDOWN AND DEPRESSURIZATION
Initiating Cue:
- You are the Reactor Operator.
- The CRS directs you to depressurize the RCS to minimize subcooling IAW Step 20 of 2-EOP-LOCA-2, POST LOCA COOLDOWN AND DEPRESSURIZATION
- Notify the CRS when Step 20 is completed.
- Your evaluator will take care of all alarms not related to your task.
Time-Critical: No
Alternate Path: Yes
Estimated Time: 5 minutes
Initial Conditions:
- The reactor was tripped when a RCS leak occurred.
- All RCPs have been stopped
- 2PR1 is inoperable with 2PR6 isolated with power removed
- The operating crew has progressed through the EOPs and is now in 2-EOP-LOCA-2, POST LOCA COOLDOWN AND DEPRESSURIZATION
Initiating Cue:
- You are the Reactor Operator.
- The CRS directs you to depressurize the RCS to minimize subcooling IAW Step 20 of 2-EOP-LOCA-2, POST LOCA COOLDOWN AND DEPRESSURIZATION
- Notify the CRS when Step 20 is completed.
- Your evaluator will take care of all alarms not related to your task.
Task Standard:
The task is satisfactorily met when the applicant has depressurized RCS using Auxiliary spray IAW step 20 of 2-EOP-LOCA-2.
The task is satisfactorily met when the applicant has depressurized RCS using Auxiliary spray IAW step 20 of 2-EOP-LOCA-2.
▶ Show Critical Steps & Key Actions
| Step | Critical Element | Standard |
|---|---|---|
| C20-1 | CAUTION: Accumulators should be isolated prior to depressurizing RCS to less than 700 psig if SI has been terminated | Verifies 21-24SJ54s closed. |
| N20-1 | NOTE: Upper head region may void during RCS depressurization if RCPs not running | Acknowledges the Note. |
| 20 | Is normal PZR spray available? | NO — with no RCPs running, normal spray is not available. |
| 20 * (cont'd) | Is at least one PZR PORV available? | YES. |
| 20 * (cont'd) | Depressurize RCS using one PZR PORV | Opens 2PR2 to attempt to depressurize RCS but it will not open. 2PR1 remains isolated and unavailable. |
| 20 * (cont'd) | Is RCS pressure dropping? | NO — observes valve not repositioning. (Alternate path begins here.) |
| 20 * (cont'd) | Depressurize RCS using Aux Spray | Opens 2CV75 (RCS Aux Spray Valve). Closes 2CV77 (Charging to Loop 23) and 2CV79 (Charging to Loop 24). Monitors RCS pressure and verifies pressure is lowering. |
| 20 (cont'd) | Operate PZR heaters as necessary to maintain PZR liquid saturated | Checks PZR temperature and determines if pressurizer heaters are required to be energized. |
| 20.1 * | When PZR level >77% (74% adverse) or RCS subcooling <10F, stop RCS depressurization | Realigns aux spray to normal: closes 2CV75 and opens 2CV77 or 2CV79. (RCS subcooling is cued as 9F and lowering.) |
Key Decision Point:
The alternate path begins when 2PR2 (PORV) fails to open — the applicant must recognize that RCS pressure is NOT dropping, then transition to the Aux Spray depressurization method by opening 2CV75 and closing 2CV77/2CV79. The applicant must also recognize the subcooling limit of <10F (cued at 9F and lowering) requires stopping the depressurization and restoring normal charging alignment.
The alternate path begins when 2PR2 (PORV) fails to open — the applicant must recognize that RCS pressure is NOT dropping, then transition to the Aux Spray depressurization method by opening 2CV75 and closing 2CV77/2CV79. The applicant must also recognize the subcooling limit of <10F (cued at 9F and lowering) requires stopping the depressurization and restoring normal charging alignment.
Ref: 2-EOP-LOCA-2 (R41) | Task: N1150090501 | System: 010 PZR Pressure Control System | K/A: A4.05 — Ability to manually operate and/or monitor in the control room: PZR Auxiliary Spray Valves | Source: New | View JPM PDF